Kingswood Homes Custom Residence - Estes Park, CO
April 28, 2006 5pm
Underground plumbing complete. Ready for inspection; Concrete
slab is next.
April 26, 2006 2pm
Basement/garage area being backfilled; radon vent lines installed;
concrete walls damp-proofed.
April 25, 2006 2pm
Basement concrete walls forms removed; Backfill of basement/garage area started.
April 21, 2006 1pm
Basement concrete walls poured.
April 20, 2006 5pm
Basement concrete wall forms ready for concrete.
April 19, 2006 3pm
Continued installation of the basement concrete wall forms.
April 18, 2006 4pm
Footer forms stripped. Began installation of the basement concrete wall forms.
April 17, 2006 2pm
Concrete footers poured.
April 14, 2006 3pm
Concrete footer forms ready for the concrete pour.
April 12, 2006 3pm
Electrical lines covered; Front Frost footings dug;
House pad excavation complete; Ready for concrete crew.
April 12, 2006 9am
Electrical line being installed.
April 11, 2006 3:30pm
Telephone and cable line installed.
April 11, 2006 2pm
Sewer line completed, passed Town inspection.
April 11, 2006 10am
Sewer line being installed.
April 10, 2006 5pm
Water and electrical trench completed.
April 10, 2006 1pm
House pad excavation complete; Starting on water and
electrical line trenches.
Looking to the north
Looking to the west
Looking to the east
Looking to the south
April 7, 2006 3pm
House pad excavation almost complete.
April 4, 2006 2pm
After blasting.
April 3, 2006 2pm
Rig for drilling holes for blasting arrived.
Area for blasting (lower/center of picture)