Kingswood Homes Custom Residence - Estes Park, CO


June 29, 2006
Rear log siding, soffit, trim, and fascia continues;
Fireplace installed; Window arch framing.











June 28, 2006
Rear log siding, soffit, and fascia continues; Water supply lines being installed.








June 27, 2006
Rear log siding continues; Rear soffit and fascia being installed.








June 26, 2006
Bay windows installed; Rear log siding continues.










June 23, 2006 PM
Door, trim, and siding installation underway; Plumbing and furnace work continues.











June 21, 2006 PM
Window installation began.










June 21, 2006 Noon
Log siding and windows arrived; Further rough plumbing.










June 20, 2006
Bay window framing essentially completed; Rough plumbing continues.








June 19, 2006
Bay window framing installed; Rough plumbing and heating began.










June 15, 2006
Roof decking completed; Bay window framing underway.




Bay Window





June 14, 2006
80% of roof decking installed.









June 13, 2006
40% of roof decking installed.








June 12, 2006
4pm - Most roof trusses installed; Roof decking started.
















June 12, 2006
Noon - Roof trusses being installed.















June 8, 2006
Roof trusses arrived.








June 2, 2006
All loft exterior and interior walls installed.











June 1, 2006
Most loft exterior walls are up; stairs to loft completed.





View from the loft to the south/front