Kingswood Homes Custom Residence - Estes Park, CO


August 31, 2006
Front exterior log siding all stained; Additional railing/balusters on front porch;
Stair skirt trim installed; Door trim continues.







Pocket door




August 30, 2006
All cabinets installed; West exterior logs stained;
Caulking on south/front side of exterior; Additional railing/balusters on front porch;
Door trim started in loft.



Master Bathroom






Loft Bathroom








August 29, 2006
Final interior doors hung; Continue staining/finishing baseboard and door trim;
Caulking on west side of exterior; Additional railing/balusters on front porch;
Most kitchen cabinets installed.











West deck



August 28, 2006
Most interior doors hung; Baseboard and door trim being stained; Cabinets arrived.

(The trim and cabinets appear a bit darker than actual, due to the cloudy weather)







Watching the progress !



August 25, 2006
Deck and porch railing and stairs continued; Started interior door hanging; Closet rods hung.












August 24, 2006 PM
Front and side posts and stairs being installed. Also started on railing components.






August 24, 2006 7am
Closets after painting












August 23, 2006
Front and side porch/deck piers concrete poured; Interior wall and ceiling priming in the early morning;
Final color sprayed in the late afternoon.





(Pictures are not very good with spraying in progress)





August 22, 2006
Additional porch posts being installed; Decking/porch balusters/railing delivered;
Additional interior trim delivered; Some closet shelving components installed.















August 21, 2006
Inside walls textured; Some work on porch/deck; Interior doors and other trim arrived.












August 18, 2006
Inside walls primed, ready for drywall texture.





August 17, 2006
Additional log siding stained; West decking completed;
Drywall taping and floating completed, ready for priming;
Additional porch log support posts installed; porch structure continued;
Front porch decking installed; Roofing installed on front porch;
Concrete porch and deck piers readied.













August 16, 2006
Exterior caulking on sides and rear of house continues; West decking being installed.
Drywall taping and floating continues on main and loft floors- about 1 day left;
Porch log support posts being installed.






August 15, 2006
Drywall taping and floating continues on main and loft floors- about 3 days left;
Exterior staining began on right front of house;
Exterior caulking on sides and rear of house;
Texture applied to basement walls; Log porch posts arrived; master bathroom shower concrete base set.











August 14, 2006
Drywall taping and floating continues on main and loft floors; Exterior caulking began.

August 11, 2006
Drywall taping and floating continues on main and loft floors.

August 10, 2006
Drywall taping and floating continues on main and loft floors.






August 9, 2006
Drywall taping and floating continues on main and loft floors.






August 8, 2006
Drywall taping and floating continues.






August 4, 2006
Drywall hanging completed. Drywall taping and floating on the upper floors is next.


August 3, 2006
Porch roof completed; Drywall hanging 99% completed.








August 2, 2006
Porch roof almost completed; Drywall hanging almost completed.













August 1, 2006
Siding Completed; Drywall hanging continues.