Kingswood Homes Custom Residence - Estes Park, CO


September 29, 2006
Electrical inspection passed; Water turned on into home; Natural gas turned on into home;
Furnace started; Cooktop ready to use; Rear door landing completed on rear porch;
Numerous plumbing fixtures useable; North/west corner of deck extended;
Master shower tile installation continues.












September 28, 2006
Remaining lights installed, power turned on to almost everything in the home;
Plumbing fixtures continue to be installed (almost completed); Appliances installed;
Garage radon pipe installed; Balcony handrail installed; Fireplace ready for stone;
Drywall patching underway; Master shower tile continues.





















September 27, 2006
Lights and plumbing fixtures continue to be installed; Basement door handrail installed;
Cooktop ready to be installed; Numerous minor trim items installed.
















September 26, 2006
Lights and fans continue to go up; Concrete poured in front and rear;
Basement door hardware installed; Furnace being prepared for startup;
Heating return air vents installed.













Basement







September 25, 2006
Tile installation continues; Furnace doors installed; Lights and fans going up;
Bathroom accessories (towel bars, hooks, etc) installed; Plumbing fixtures installation began.

Kitchen


Master Bathroom



Loft Fans




Loft bathroom


Furnace



September 23, 2006
Tile installation continues; Basement closet door installed; Wire mesh installed on exterior, ready for stone.



Kitchen


Basement



September 22, 2006
Tile installation continues; Basement doors and trim installation completed (except furnace door).

Basement doors and trim



Master Bathroom back-splash



September 21, 2006
Tile installation continues; Staining of basement trim completed;
Basement doors and trim being installed.

Basement tile grouted


Basement doors and trim



Kitchen back-splash




First cleaning of bathtubs



September 20, 2006
Tile installation continues; Electrical plugs, switches and light installation began;
Concrete forms ready in rear, along garage, and on front steps; Staining of basement trim continues;
Master bathroom countertop set; Loft bathroom cabinet and countertop set.



Basement






Master shower


Master bathroom



Loft






September 19, 2006
Tile installation continues; Door handles installed on interior doors; Cabinet toe-kicks installed;
Closet rods installed; Forms being set for concrete in rear, along garage, and front steps;
Staining of basement trim.



In basement












September 18, 2006
Staining/Painting of front porch continues; Tile installation continues; Final window trim installed;
Most interior doors hung; Kitchen counter log posts installed; Basement doors and wood trim started;
Gas meter installed; Window seat constructed; garage door openers installed.







September 14, 2006
Staining of front porch continues; Floor tile grouted in various places;
Kitchen countertops installed; Doors and basement trim arrived.














September 13, 2006
Staining of front porch and continued staining of some interior trim;
Painting of basement; Floor tile grouted in entry/kitchen and master bathroom.




(The basement paint is same color as the rest of the house, though it looks a little different in this particular light)



September 12, 2006
Staining/finishing of doors and trim continues;
Windows sills, handrails, and stair skirts installed. Floor tile installation continues.









September 11, 2006
Staining/finishing of doors and window sills continues;
Floor tile installation continues.

Master Bathroom


Washer area in utilty room


Then later in the utility room


Kitchen



September 8, 2006
Staining/finishing of doors, door jams, log headers, and window sills continues;
Floor tile installation continues; Electrical power switched to permanent house power.


September 7, 2006
Stair hand-rails installed; T&G vertical boards installed on the back side of kitchen island;
Tile floor installation began;
Staining of doors, door jams, log headers, and window sills continues.



















September 6, 2006
All baseboard completed for carpeted areas; All window sill trim completed (but not yet stained);
Trench dug to run electrical to house; All tile floor underlayment installed;
Began staining of doors and door jams.



The carpet and tile












September 5, 2006
Floor tile backerboard installation began; Began window sill trim installation; Carpet and floor tile delivered.


September 2, 2006
Most loft baseboard completed; Installation of baseboard on main level started;
Countertop installed in utility room; Stairwell knee-wall and window sill trim started.

Loft



Master bedroom


Utility room



September 1, 2006
Front porch essentially complete; All door trim installed (but not stained);
Loft closets baseboard installed; Started on baseboards in the loft main rooms.