Kingswood Homes Custom Residence - Estes Park, CO


October 20, 2006





















October 16, 2006
Front stone grouting completed; Gutters completed; Asphalt driveway next.










October 13, 2006
Front stone grouting began; Phone hooked up;
Gutters started; Minor outside staining touchup; Move in day tomorrow!


October 12, 2006
Fireplace started; Certificate of Occupancy permit granted; Ready for move-in.














October 11, 2006
Paint touchup; House cleaning; Other minor items addressed.

October 10, 2006
Paint touchup; Front porch post finished; Master bathroom vanity faucet installed;
Minor electrical items finished.








October 9, 2006
Carpet installed; Front porch steps/rail installed; Final grading and driveway shift completed.
















Basement




October 8, 2006
Front stone almost completed, grouting remains.





October 7, 2006
Stone continues to be installed; Fireplace stone completed. All permanent door handles/locks installed;
Walls and floors cleaned - ready for carpet.










October 6, 2006
Touch-up painting; Stone being installed; Door handle sets being installed.








October 5, 2006
Tile installation completed; Tub plumbing fixtures installed in the loft and basement bathroom;
Master shower trim installed; Basement ready for carpet; Finalizing all stained components.














October 4, 2006
Exterior doors being painted; Low-voltage wiring installation continues;
Tile installation continues in master bathroom; Recessed light fixture and speaker trim being painted.











October 3, 2006
Mirrors installed; Painter continues to work on un-stained pieces;
Basement doors continue to being stained; Rear patio steps completed;
Stairs built for front steps to landing; Tile continues in master bathroom;
The basement is essentially completed (except for plumbing fixtures and carpet).










October 2, 2006
Painter works on un-stained pieces; Basement doors being stained; Utility room cabinets installed;
Removed paper around concrete post bases; Garage cleaned in preparation for carpet cutting;
Low voltage wiring underway; Tile continues in master bathroom;
Driveway cleared in preparation for final grading; Porch stair treads secured.