Kingswood Homes Custom Residence - Estes Park, CO
January 30, 2006 - 2pm
Windows and doors being installed.
January 27, 2006 8am
Taken just before the concrete was poured.
The roof decking was completed January 26.
Work on additional basement walls and interior stairs was
proceeding.
January 26, 2006 8am
January 25, 2006 8am
January 24, 2006
noon
The garage roof trusses and decking were installed January 23.
January 20, 2006
3pm
January 18, 2006
8am, main floor walls raised
January 11, 2006
January 9, 2006
January 5, 2006 - The day after the basement slab poured.
January 4, 2006
January 2, 2006