Kingswood Homes Custom Residence - Estes Park, CO
April 28, 2006 5pm
Final grading complete; Gutters installed; Bathroom mirrors
and shower doors installed.
Guest Bathroom
Master Bathroom
April 26, 2006 2pm
Final grading underway.
April 21, 2006 3pm
Electrical service switched to permanent power by Town.
April 21, 2006 8am
Painting and staining completed.
April 20, 2006
Window screens and handles installed; Touchup painting.
April 19, 2006 3pm
Carpet installed.
Most carpet now covered with plastic
Door Bell
Extra carpet sections in garage
April 13, 2006 3pm
99% of all electrical fixtures, plugs, outlets, and smoke alarms installed.
(Red items on ceilings are smoke alarms, with a red cover)
Utility Room
Kitchen
Over sink
In stairwell
Master bedroom closet
220v in garage
April 13, 2006 8am
Most appliances installed.
April 12, 2006 4pm
75% of light fixtures installed.
April 12, 2006 2pm
Appliance cabinet installed; Stone work is 99% complete.
April 12, 2006 8am
April 11, 2006 2pm
April 10, 2006 4pm
Deck 99% completed; Basement door trim installed. Stone work nears completion.
April 9, 2006 3pm
Deck almost completed
April 7, 2006 4pm
Additional deck work
April 6, 2006 3pm
Exterior stone work continued;
Plumbing fixtures being installed;
Electrical switches and plates being installed;
Additional deck work
April 6, 2006 8am
Exterior stone work continued;
Master bathroom countertop installed;
Kitchen counter prepared for stove;
Door bumpers and towel bars installed.
April 5, 2006
Exterior stone work continued; Door Handles installed.
Finished stone, with (wet) mortar between stone
April 4, 2006
Exterior stone work continued; Painted exterior doors hung;
Basement doors installed.
(Pictures taken at several times during the day)
April 3, 2006 2pm
Exterior stone work began; Exterior doors being painted;
Basement doors being installed