Kingswood Homes -Custom Home - Estes Park, CO
March 29, 2007
Final section of new water line installed. Framers are next.
Two water shut-off valves
March 27, 2007
Excavation around home nearly complete;
Electric service to new home site energized;
Next will be additional framing materials;
Remainder of new water line up driveway may also be installed soon.
Area in front of home
Area behind home
Driveway to new home
March 26, 2007
Garage slab poured as well as entry concrete pad.
March 22, 2007
Backfill 90% complete ; lumber starting to arrive;
garage slab pour next main item.
March 21, 2007
Damp-Proofing applied to concrete walls. Backfill is next.
March 20, 2007
Concrete walls completed. Ready for damp-proofing, backfill, and
garage slab preparation.
March 19, 2007
Concrete walls being poured.
March 16, 2007
Concrete wall forms being installed;
New electrical line, TV cable, and telephone
cable being installed in the trench.
Concrete walls poured next.
March 15, 2007 2pm
Concrete footer poured;
3/4 of utility trenches dug.
March 15, 2007 8am
Excavation for utility trench continues; Concrete footer forms ready for concrete.
March 14, 2007
Excavation for utility trench continues; Concrete footer forms being installed.
March 13, 2007 3pm
Excavation completed on house pad; utility trench being dug.
Concrete forms are next.
March 13, 2007 8am
Excavation underway.
March 8, 2007
Lot before any construction.
Left side of home site
Large fallen tree is at corner of garage
Looking up new driveway from new home