Kingswood Homes - Custom Home - Estes Park, CO
April 30, 2007
Roof decking and fascia completed.
April 28, 2007
Roof decking almost completed.
April 27, 2007
Roof framing almost completed.
April 26, 2007 morning - Roof going up.
April 24, 2007 - Loft walls continue.
April 22, 2007 - Stairs continued, loft walls framing.
April 20, 2007 - morning - Most of loft decking installed; stairs started;
additional windows installed, further framing.
April 19, 2007 - Framing continues.
April 18, 2007 - Framing and siding continues
April 17, 2007 - Framing continues
April 16, 2007 - Framing in progress
April 2007
View from the main level
April 04, 2007
Cabin getting a new roof.
April 02, 2007
Additional building materials arrived.