Kingswood Homes - Custom Home - Estes Park, CO
May 31, 2007 Afternoon
Drywall continues; 90% completed; exterior staining completed;
Final roofing being installed.
May 31, 2007 Morning
Drywall continues - hanging should be done in a day or 2;
exterior staining continues - should finish today;
drywall finishing should start next week.
May 30, 2007
Drywall continues; exterior staining continues.
May 29, 2007
Drywall started; Roof shingles started; Garage door opener installed.
May 27, 2007
Insulation completed;
Floor protection paper installed; Sheetrock stocked
(installing drywall is next);
West exterior wall stain dried (further staining this coming
week).
May 25, 2007
Stain on west side.
May 24, 2007
Gas line installed; siding completed.
May 23, 2007
Rough electrical completed; rough plumbing almost done; Insulation in the next couple days.
May 22, 2007
Rough electrical and plumbing continues.
May 21, 2007
Siding almost complete; Rough electrical and plumbing continues.
May 18, 2007
Siding continues on final wall; Rough electrical and plumbing continues;
Shingles stocked on roof.
May 17, 2007
Siding continues on final wall; Rough electrical and plumbing continues.
May 16, 2007 morning
Siding continues; Rough electrical and plumbing continues.
May 14, 2007
Siding continues; Rough electrical started.
May 8, 2007
Upper siding and soffit being installed; Rough furnace ducting continues; fireplace set in place.
May 3, 2007
Garage door installed; tar-paper installed on roof; Rough furnace ducting continues.
May 2, 2007
Rough furnace ducting began; entry overhang installed.
May 1, 2007
Almost all framing completed.