June 29, 2007
Propane tank installed; electrical plugs/switches being activated.









June 28, 2007
Some trim pre-finished (pictures taken in dark garage); Next items are propane tank install,
trim carpenter, and septic system.





June 27, 2007
Cabinets arrived. Power switched into home.








June 26, 2007
Doors and trim arrived.






June 23, 2007
Fireplace completed; new propane location prepared.









June 21, 2007
Fireplace work continues, mainly grouting remains.






June 20, 2007
Fireplace work started.






June 18, 2007
Gutters installed; Furnace unit installed in crawl-space.






June 15, 2007
Interior panted.













June 12, 2007
Propane line dug; Flat area for propane tank made; Started on septic tank and lines.





Sewer line from house




June 10, 2007
Home cleaned; Painting inside will be next larger task.












June 9, 2007
Texture applied to sheetrock.









June 8, 2007
Sheetrock ready for texture.








June 6, 2007
Morning - Sheetrock taping & floating continues.







June 4, 2007
Sheetrock taping & floating started.







June 1, 2007
Sheetrock hanging completed; drywall taping & floating next; roof completed.