Kingswood Homes - Custom Home - Estes Park, CO



July 31, 2007
Tile and counters continues.








July 29, 2007
Tile continues.

Entry


Master Bath



Loft





July 28, 2007 7am
Tile installation continues; decking started.












July 27, 2007
Countertop arrived; tile installation began.



July 25, 2007
Trim continues; tile preparation materials staged.




July 24, 2007
Trim continues.





July 23, 2007
Trim and plumbing continues; water turned on into house.







July 20, 2007
Trim and plumbing continues; Final electrical fixtures installed - passed State Inspection.











July 19, 2007 5pm
Trim and plumbing continues.









July 19, 2007 8am
Trim continues; plumbing started.





July 17, 2007
Trim and lights continues.







July 17, 2007 4pm
Trim and septic continues; granite installed; almost every light installed;
improved main level doors installed.
















July 17, 2007 7am
Trim and septic continues.

Powder Room


Loft Bathroom










July 14, 2007
Trim, electrical, and septic continues.












July 13, 2007
Trim continues.




July 12, 2007
Trim and light installation continues.





July 11, 2007
Trim and light installation continues.








July 10, 2007
Trim continues.










Pantry shelving




July 7, 2007
Sample floor/wall tile and kitchen backsplash tile.


Kitchen backsplash tile





July 6, 2007
Trim installation underway.






July 4, 2007
Electrical components installation continues.








July 3, 2007
Septic system continues; Light fixture installation started;
Trim installation continues; Most cabinets installed.











Master Bathroom


Loft wall fixtures






July 2, 2007
Septic system being installed; Trim installation started