Kingswood Homes - Custom Home - Estes Park, CO
April 30, 2007 morning
House concrete slab installed.
April 27, 2007 morning
Ready for concrete slab.
April 25, 2007 4pm
Under-slab plumbing ready for inspection and backfill.
April 25, 2007 Noon
Under-slab plumbing being installed.
April 24, 2007
Damp-proofing completed (yesterday); interior backfill underway, radon venting, foundation
insulation.
April 23, 2007
Walls forms stripped. Damp-proofing and some backfill is next.
April 20, 2007 PM
Concrete walls poured.
April 19, 2007 Morning
Wall forms being installed.
April 17, 2007
Foundation footer forms removed. Wall forms next.
April 16, 2007 PM
Foundation footer concrete poured; underground wiring ditch filled.
April 16, 2007 AM
Foundation footer concrete forms and underground wiring being installed.
April 10, 2007 PM
Excavation continues.
April 10, 2007 Early morning
Excavation continues. Jack hammer used in some hard areas.
April 9, 2007
Excavation Begins
The lot before any construction.