Kingswood Homes - Custom Home - Estes Park, CO
May 31, 2007 afternoon
Roof structure going up.
May 29, 2007 afternoon
Roof Trusses up.
May 29, 2007 morning
Roof Trusses being installed.
May 24, 2007
Framing continues.
May 23, 2007
Framing continues; garage slab poured.
elk helping with the trash
May 22, 2007
Framing continues; concrete prepped and poured
May 21, 2007
Framing continues
May 18, 2007
Framing continues
May 17, 2007
Framing continues
May 16, 2007
Framing continues
May 15, 2007
Framing continues
May 14, 2007
Framing continues
May 8, 2007
Framing continues
May 7, 2007
Framing continues
May 4, 2007
Framing began; Garage area being backfilled.
May 2, 2007
First load of framing material arrived; Street cut again for the sewer line.
May 1, 2007
Getting setup for framing.
Road blocked while electrical cable installed underground to property