September 28, 2007

Painting underway
(walls colors don't show up well under current light conditions).













September 25, 2007

Drywall texture applied; Painting next.








September 21, 2007

Wood ceiling and walls in Sunroom underway; Final drywall prep before planned texturing next week.







September 20, 2007

Wood ceiling and walls in Sunroom underway; Drywall texturing within the next couple days.






September 19, 2007

Drywall tape & floating almost completed.







September 14, 2007

Drywall tape & floating continues.







September 13, 2007

Drywall tape & floating continues.








September 12, 2007

Drywall tape & floating continues.







September 11, 2007

Drywall tape & floating began.








September 9, 2007

Drywall hanging completed













September 7, 2007

Drywall hanging almost completed









September 6, 2007

Drywall hanging continues; Main level about 85% complete; basement about 50% complete.










September 5, 2007

Drywall installation begins.