Day 9 - April 13, 2005
Main work was utility ditches.
The first several pictures are from the front of the lot to the house.
Sewer line in driveway
Day 8 - April 12, 2005
The building hole is complete. Some work on utility ditches remains.
Maximum depth of hole = 17 ft at rear corner; Minimum depth of hole = 3 ft at front corner;
Average hole depth = 8 ft
Day 7 - April 11, 2005
Day 4 - April 8, 2005 (taken on 2 different days in different light)
Day 3 - April 7, 2005
Day 2 - April 6, 2005