Day 44 - Wednesday - May 18, 2005
Basement/Garage concrete floor poured. 25 yards concrete - 3 trucks.




























Day 42 - May 16, 2005
Rough basement underground plumbing finished (had been waiting on concrete cut for basement tub). Pressure test system. Inspection and covering all pipes on May 17.



Day 40 - May 14, 2005
More rough basement underground plumbing.

















Day 39 - May 13, 2005
Started rough basement underground plumbing.




Day 37 - May 11, 2005
Final backfill of garage and basement. Ready for rough plumbing.













Day 36 - May 10, 2005
Adjust wiring into house; Radon tubes in basement; backfill basement/garage area













Day 35 - May 9, 2005
Waterproofing on concrete walls applied
(DECO Brand latex waterproofing)








Day 31 - May 5, 2005
Concrete walls exposed
The tallest walls are about 11 ft high









Day 30 - May 4, 2005
Concrete walls poured















Day 18 - April 22, 2005
Footer forms removed - Walls are next












Day 16 - April 20, 2005
Footer concrete pour - 3 trucks of concrete