Kingswood Homes Custom Home


Day 112, July 25, 2005
More interior main floor walls raised.





Day 109, July 22, 2005
More interior main floor walls raised.






Day 108, July 21, 2005
More interior main floor walls raised. Stairs from basement in.



Master bathroom

Master bedroom closet and utility room closet

Study (left) and Master Bedroom (right)

Stairs from basement to 1st floor




Day 107, July 20, 2005
Interior main floor walls under construction. Stairs being prepared.






Day 106, July 19, 2005
Additional main level walls raised (over the garage , on the east side of house).
Some work on stairs from/in the basement.










Day 105, July 18, 2005
Front main wall installed, along with some side walls on the main floor.




















Day 95, July 7, 2005
Concrete patio, garage door apron, stair landing, and front basement entry door conrete pad poured this week.
First walls on the main floor went up.


Front basement door concrete pad

Garage concrete apron

Deck stairs landing

Rear Patio

Rear main level wall up. Front wall being prepared on the floor before being raised.





Day 88, July 1, 2005
Concrete pier beams forms were poured on June 29.
Siding, fascia, soffit, and trim arrived June 30. It will be pre-stained in the garage before it is installed.
The materials for the main floor walls arrived. The framers should restart July 5, 2005.













The view out the back door, from the rear patio looking up the mountain.



Day 85, June 28, 2005
Concrete pier beams forms (for the deck) are ready for conrete.








Day 64 - Tuesday - June 7, 2005
Grading and backfill complete.
Next will either be exterior concrete work (deck posts, concrete apron in front of garage and front basement door, and rear patio slab) or framers.

Driveway

Looking up from driveway


Looking down hill from west side of house (this area has been buried in about 40 ft of dirt for 60 days).

Looking out the basement door (on the front of the house).

Looking out the garage doors



The driveway/parking area.

The front of the walk-out basement. Almost all of this side of the basement will be covered with cultured stone.



Day 63 - Monday - June 6, 2005
Only a little dirt removal remaining. Other grading and backfll complete.
Next will either be exterior concrete work (deck posts, concrete apron in front of garage and front basement door, and rear patio slab) or framers.










Day 60 - Friday - June 3, 2005
Backfill around house essentially completed. Additional dirt to be removed June 6. No more gigantic ditches around the house.

View of garage side and new rear grading, from the road.


Along the front of the house (the basement).


Along the back of the house, taken from the garage side.


Along the rear of the house.


Along the rear of the house.


View out the back door (the red line on the floor is the back door location).


View along the west side of the house, facing forward.


Along the front of the house, taken from the west side looking down.


Along the west side of the house, looking toward the rear



Day 59 - Thursday - June 2, 2005
Beginning of backfill around house.

Foundation drain tile/pipe also has stub for gutters (shown is corner by garage, as well as southwest house corner.






Day 53 - Friday - May 27, 2005
Remainder of main floor joists installed and all the plywood sub-floor installed. The framers will leave for a week or two, while the excavators backfill the huge space around the house (and get rid of most of any excess dirt/rock).





View from the living room below

View from the dining room below




Day 52 - Thursday - May 26, 2005
Most Main Floor Joists Installed. Plywood Sub-floor Next.










Day 51 - Wednesday - May 25, 2005














Day 50 - Tuesday - May 24, 2005









Day 49 - Monday - May 23, 2005
Basement/Garage Walls started.





Day 46 - Friday - May 20, 2005
Initial Framing Materials & Plannning.