Kingswood Homes Custom Home


Day 154, Monday, September 5, 2005
Loft and attic front interior wall framed. 95% of all framing is complete. Wall blocking and pocket door framing next. Windows and doors coming soon, as well as the deck structure. Furnace people, plumbers, and electricians should start this week.








Another picture of the marked sewer line.



Day 152, Saturday, September 3, 2005
Tar paper and Ice and Water Shield on roof.






Great room

Kitchen area. Orange marks are the floor cabinets.


Loft area walls, almost completed


All of the exterior doors and about half of the windows arrived.The door with glass is the main entry door. (picture is reversed to show door)


The staining area, used for all exterior trim and siding over a 6 week period.


A few pictures of the sewer line placement, along side of driveway.





Day 150, Thursday, September 1, 2005
Fascia completed. Rear roof sheating completed.
Tar-paper on roof next, then decking and siding.

First picture is early in the day, before roofing finished.




Next is loft bathrooms/bedroms being framed.

Next is view from dining area into the Living Room area.

Stairs up to loft.

Kitchen area

From the Living Room/Great room, looking into the loft, the to the dining area.






Day 149, Wednesday, August 31, 2005
Lower to upper roof wall completed. Rear look-outs completed. Fascia continued. Rear roof sheathing will be tomorrow.









Place on side wall where direct vent stove will be, with a stove pipe going out the side of the house (in the box built).



Day 147, Monday, August 29, 2005
All of the front roof sheathing on, fascia started.








Day 144, Friday, August 26, 2005
Roof rafters stablization. Built most of loft interior walls.










Day 142, Wednesday, August 24, 2005
Roof rafters almost complete.








Day 141, Tuesday, August 23, 2005
More roof rafters.









Day 140, August 22, 2005
More roof rafters, final top beam installed.








Day 137, August 19, 2005
More roof rafters, and some roof sheathing.










Day 135, August 17, 2005
Large posts leveled and secured. Roof rafters started.






Day 133, August 15, 2005
Numerous large beams set. Some roof rafters next. Loft tub arrived.








Day 127, August 9, 2005
Rear upper walls raised. These are the final exterior walls. Preparing for the roof beams and a portion of the deck are next.












Day 123, August 5, 2005
Rear upper wall being prepared.




Day 121, August 3, 2005
Stairs to loft installed. Numerous bracing put up.


Study

Kitchen area. Red lines on floor are cabinet areas. The window in the picture is the one over the kitchen sink.



Day 116, July 29, 2005
Loft sub-floor installed. Large beam can be seen from the front.






View from the loft (2nd floor).



Looking down into the great room/dining room from loft.




Day 115, July 28, 2005
Loft floor joists installed, some loft decking.






Day 114, July 27, 2005
Large interior beam raised and set into place.