February 23, 2007
2nd Level floor being installed.


















February 18, 2007
Main level walls being installed.














February 13, 2007
Main level walls being installed.


















February 9, 2007
Main floor sub-floor installed; Garage slab poured.







February 8, 2007
Main floor sub-floor being installed.












February 4, 2007
Wall sill plates installed. Water storage tank on premise.