Kingswood Homes -Custom Home - Estes Park, CO


March 30, 2007
Windows and exterior doors installed. Rough plumbing installation began. Garage doors installed.














March 25, 2007
Roof structure installation continues. Windows and exterior doors will be next.









March 16, 2007
Roof structure installation continues.












March 11, 2007
Roof structure being installed.























March 4, 2007
2nd Level sub-floor completed. Ready for roof structure.