Kingswood Homes - Custom Home - Estes Park, CO
May 30, 2007
Drywall continues; stucco continues.
May 29, 2007
Drywall continues; stucco continues; roof installed.
May 23, 2007
Drywall continues; stucco continues.
May 21, 2007
Drywall continues; stucco continues.
May 16, 2007
Drywall continues; stucco continues; heat working.
May 14, 2007
Drywall continues; stucco underway; roof getting completed.
May 8, 2007
Drywall started; Some trees removed; ready for house electrical power.
May 6, 2007
Insulation almost completed, drywall next.
May 3, 2007
Gypcrete floors installed.
May 1, 2007
Rough wiring and plumbing completed. Soffit and siding being installed.
Ready for gypcrete floors.