Kingswood Homes - Custom Home - Estes Park, CO


June 29, 2007 11am

Loft bench tile almost completed; grouting in loft bathrooms; loft bathroom doors swapped;
vinyl in loft bathrooms installed; door trim continues.



(Grout being installed)







June 28, 2007

More cabinets staged; Master bath floor started.;Cooktop tested for fit.




















June 27, 2007

More cabinet parts delivered; Tile in master bath floor started.







June 26, 2007 4pm

Cabinets being installed; Tile continues in loft bathrooms.

(Cloudy day, poor natural light)














June 26, 2007 8am

Cabinets on site, installation begins.









June 25, 2007

Mockup of bathroom windows.







June 24, 2007

Hardwood floors - finish applied.












Floors now covered





June 21, 2007

Septic vault relocation completed-waiting on inspection; Remainder of hardwood floor installed;
All doors hung; trim continues; Balcony railing started;
Tile in other loft bath started.





































June 20, 2007 4pm

Septic vault relocated; Kitchen area wood floor down.






















June 20, 2007 noon

Fireplace stone near the end; tile started in loft baths; wood floor being installed.







June 19, 2007

Gutters installed; Mantel installed; Fireplace stone continues.













June 18, 2007

Exterior stone work completed; Fireplace stone started; master bathroom floor prepped for tile.










June 15, 2007 morning

Trim continues; stone work continues; some vinyl installed.








June 14, 2007

Trim continues; outside stone work started.

















June 13, 2007

Trim staining underway; doors being installed.








June 11, 2007

Hardware floor layed in place, to allow to acclimate.




June 8, 2007

Painting began on interior walls; trim and doors on-site; exterior being prepped for stone.




























June 6, 2007

Interior walls primed; exterior scaffolding removed.


















June 5, 2007

Floors cleaned, ready for paint.








June 4, 2007

Sheetrock texture completed; Inside painting next; Exterior stone soon.









June 3, 2007

Sheetrock taping/floating completed, texture next; exterior stucco completed; exterior stone next.