Kingswood Homes - Custom Home - Estes Park, CO
June 29, 2007 11am
Loft bench tile almost completed;
grouting in loft bathrooms;
loft bathroom doors swapped;
vinyl in loft bathrooms installed;
door trim continues.
(Grout being installed)
June 28, 2007
More cabinets staged; Master bath floor started.;Cooktop tested for fit.
June 27, 2007
More cabinet parts delivered;
Tile in master bath floor started.
June 26, 2007 4pm
Cabinets being installed; Tile continues in loft bathrooms.
(Cloudy day, poor natural light)
June 26, 2007 8am
Cabinets on site, installation begins.
June 25, 2007
Mockup of bathroom windows.
June 24, 2007
Hardwood floors - finish applied.
Floors now covered
June 21, 2007
Septic vault relocation completed-waiting on inspection;
Remainder of hardwood floor installed;
All doors hung; trim continues;
Balcony railing started;
Tile in other loft bath started.
June 20, 2007 4pm
Septic vault relocated; Kitchen area wood floor down.
June 20, 2007 noon
Fireplace stone near the end; tile started in loft baths; wood floor being installed.
June 19, 2007
Gutters installed; Mantel installed; Fireplace stone continues.
June 18, 2007
Exterior stone work completed; Fireplace stone started;
master bathroom floor prepped for tile.
June 15, 2007 morning
Trim continues; stone work continues; some vinyl installed.
June 14, 2007
Trim continues; outside stone work started.
June 13, 2007
Trim staining underway; doors being installed.
June 11, 2007
Hardware floor layed in place, to allow to acclimate.
June 8, 2007
Painting began on interior walls; trim and doors on-site;
exterior being prepped for stone.
June 6, 2007
Interior walls primed; exterior scaffolding removed.
June 5, 2007
Floors cleaned, ready for paint.
June 4, 2007
Sheetrock texture completed; Inside painting next;
Exterior stone soon.
June 3, 2007
Sheetrock taping/floating completed, texture next;
exterior stucco completed; exterior stone next.