Kingswood Homes - Custom Home - Estes Park, CO


July 31, 2007

Electricial, decking, trim, painting, tile continues.


















July 30, 2007

Electricial, decking, trim, staining continues.












July 29, 2007

Tile and electricial continues. Decking on-site








July 27, 2007 3pm

Staining and electricial continues.




July 27, 2007 9am

Plumbing continues; tile continues; additional cabinets being installed; electricial continues.








July 26, 2007

Plumbing continues; tile continues; additional cabinets being installed; electricial started.






















July 25, 2007 10am

Tile, deck, and staining continues.












July 23, 2007 noon

Tile, deck, and staining continues.












July 20, 2007 noon

Tile, deck, and staining continues.










July 19, 2007 4pm

Tile, trim, and deck continues.








July 19, 2007 8am

Tile continues; Plumbing continues; Trim continues; Electrical continues; deck started.
















July 18, 2007

Tile continues; Plumbing continues; Trim continues.









July 17, 2007

Staining continues; Tile continues; Granite completed; baseboard heater being installed.















July 16, 2007

Staining continues; Master bathroom wall textured; Most of kitchen granite installed.

















July 14, 2007

Staining, plumbing, and drywall adjustment continues.










July 13, 2007

Trim, staining, plumbing continues.












July 12, 2007

Trim and staining continues; Plumber started.



July 11, 2007

Trim and staining continues.





July 10, 2007

Trim and staining continues.




July 9, 2007

Trim continues.







July 8, 2007

Trim continues.














July 6, 2007

Study installed; Trim continues.








July 5, 2007

Trim continues, granite measured.









July 4, 2007

Tile continues.










July 3, 2007

Tile continues.











July 2, 2007

Trim & cabinets continue; Master shower base set.