Kingswood Homes Custom Remodel - Estes Park, CO


January 31, 2008
North addition.














January 30, 2008
North addition.











January 28, 2008
North addition.










January 27, 2008
North addition.











January 25, 2008 PM
North addition.










January 25, 2008 AM
North addition.









January 24, 2008 AM
New basement framing; North addition.











January 23, 2008 AM
New basement framing.








January 19, 2008
North addition underway.







January 17, 2008 AM
South addition continues; North addition underway; temporary bracing in living room.











January 17, 2008
South addition continues - new rooms formed.


Bedroom into sun room



Tub & shower area


Shower









January 16, 2008
South addition continues; South addition opened to/from existing house; Column bases readied for concrete on north/east.






January 15, 2008
South addition continues; windows and door installed; tyvek walls; North-east trusses on-site; beginning NE addition.













Northeast addition



January 13, 2008
South addition continues.









January 11, 2008
South addition continues; Underground wire installed, inspected, and back-filled;
Excavation for 4 column pads; garage apron area prepped.








4 Column Pad areas








January 10, 2008
South addition continues; Underground wire being installed.









January 9, 2008
South addition continues; electrical trench being dug.










January 8, 2008
South addition trusses going up.










January 6, 2008
South addition framing continues. North addition concrete installed.










January 3, 2008
South addition framing continues; north addition ready for concrete.










January 2, 2008
Stairs continue; South addition continues; north addition rough plumbing.