Kingswood Homes Custom Remodel - Estes Park, CO
April 30, 2008
Wood floors, electrical, and trim underway.
Wood floor installation completed today. Sanding, sealing, coating next.
April 29, 2008
Wood floors, electrical, and trim underway.
April 28, 2008 PM
Wood floors underway.
April 28, 2008 (early)
Wood floors underway.
April 26, 2008
Tile, vinyl, and trim.
All tile and vinyl completed, except kitchen. Ready for hardwood floors.
Vinyl in storage room
Master bathroom caulked, cabinet doors replaced.
April 25, 2008
Tile and trim.
Underlayment for vinyl in storage room
White tile grouted; Only caulking of tile in master bathroom remains.
April 24, 2008
Tile, trim, and electrical.
April 23, 2008
Tile, trim, and electrical.
Portions of master bathroom grouted.
Toe kick for kitchen and master bathroom
April 22, 2008
Tile, trim, and electrical.
April 21, 2008
Tile, trim, and cabinets.
April 20, 2008
Siding and cabinets.
Master Tub
Rear Entry floor
April 18, 2008
Tile continues - floors almost all completed; kitchen upper cabinets installation underway.
Now Grouted
Being grouted
April 17, 2008
Tile continues; kitchen upper cabinets onsite;
kitchen desktop and living room shelves onsite;
Kitchen and hallway grouted.
Original rock around home
Sun Room
April 16, 2008
Tile continues.
Entry tile area grouted
Sidewalk area
Patio Threshold
North main entrance threshold
Rear door threshold
April 15, 2008
Tile continues; Stone completed; exterior caulking; Hardwood onsite.
April 14, 2008
Power switch completed; Tile continues; Stone almost completed;
exterior caulking; lights onsite.
April 11, 2008
Tile continues - Entry Area.
Work started on changing the power to underground
The one new basement door
April 10, 2008
Tile continues - Master Bathroom.
April 9, 2008 3pm
Soapstone counters installed; Tile underway; Siding continues.
Lumina Tile
Master Bathroom floor/wall tile example
April 9, 2008 noon
Soapstone counters being installed. (Counters were not cleaned at this point).
April 9, 2008 8am
Tile underway; siding continues; doors hung.
April 5, 2008
Stair pickets on-site.
April 4, 2008
Lower cabinets installed; Soapstone counters measured; siding continues; stair posts onsite.
April 3, 2008
Cabinets being installed; New pressure pump being installed;
kitchen and bathroom floor heater mesh onsite.
Under tile heater mesh
April 3, 2008
Trim pre-staining continues; Cabinets being installed..
(Dishwasher goes between these 2 cabinets)
South wall, near Frig
Master Bathroom (color does not show well on these pictures)
April 2, 2008
Trim pre-staining continues; Siding continues.
Master Bath walls
Main handrail
Master Bathroom floor
April 1, 2008
Kitchen base cabinets onsite; Master Bath cabinets onsite;
Trim pre-staining underway; Siding continues.
Baseboard trim - stained to match cabinets
Trim stain