Kingswood Homes Custom Remodel - Estes Park, CO
October 31, 2007
Rough wiring completed;
Roofing arrived;
Garage doors being installed
October 29, 2007
Soffit/Entry Door installed.
October 28, 2007
New garage bay framed.
October 26, 2007
Garage slab being poured; framing & siding materials onsite.
October 23, 2007
Garage section ready for slab-prep and slab.
October 22, 2007
Garage section ready for backfill, slab-prep, then slab.
October 19, 2007
Garage footer/foundation walls poured.
October 17, 2007
Garage footer/foundation walls - concrete forms installed.
October 16, 2007
Garage excavation completed.
October 15, 2007
Garage excavation begins
Early 2007
Before any work began
Garage
House