Kingswood Homes Custom Residence - Estes Park, CO
March 29, 2006
Front entry deck being installed. Rough plumbing completed.
Interior rough electrical 90% completed.
Roof shingles ready to be installed.
March 17, 2006
The roof tarpaper installed; Rough plumbing 75% complete.
Windows being installed. All interior framing complete.
March 4, 2006
The roof sheathing was installed.
February 23, 2006
The roof trusses were installed.
February 11, 2006
The loft walls are nearing completion.
The backfill around the house nearing completion.
February 7, 2006
The loft sub-floor was completed, now getting ready for the loft walls.
The backfill around the house began.
February 4, 2006
The framing of the main floor is nearly finished.
Work started on the loft flooring.
January 29, 2006
The framing of the main floor is underway.
The majority of the basement framing is complete.
January 12, 2006 - Ready for the basement concrete