Kingswood Homes Custom Residence - Estes Park, CO
August 18, 2006
All interior and exterior stone completed; driveway installed;
finishing touches underway.
July 29, 2006
Exterior stone installed; hand railing installed; additional
plumbing fixtures installed.
July 13, 2006
Ceramic tile almost completed; staining of hand railing;
granite countertops installed.
July 3, 2006
Electrical lights and fixtures being installed;
Trim installation continues.
June 27, 2006
Ceramic tile installation continues;
Electrical fixtures being installed;
Trim installation continues;
Deck railing being installed.
June 15, 2006
Ceramic tile installation continues;
Plumbing and heating fixtures being installed;
Hardwood flooring installed; Concrete apron installed;
Trim installation continues.
Main entry tile
Window sills being installed
Hardwood floors in dining area and kitchen
June 7, 2006
Ceramic tile being installed;
Door and baseboard trim being installed.